Leyhill WRC AMP8 Improvements

Successfully delivering the Leyhill WRC AMP8 upgrade with advanced MBBR technology, low-carbon civil solutions, and enhanced infrastructure to achieve outstanding ammonia compliance ahead of the 2026 regulatory deadline.

Overview

Leyhill WRC (Wotton-Under-Edge) was upgraded under AMP8 to meet a new Environment Agency ammonia consent of 3.8 mg/L by the 31st March 2026 regulatory deadline. The scheme was delivered on programme, achieving a significantly improved ammonia result of 0.67 mg/L during commissioning.

Objectives
  • Achieve new ammonia limit of 3.8 mg/L
  • Install tertiary MBBR technology
  • Upgrade electrical infrastructure
  • Deliver works ahead of the 2026 deadline
  • Reduce carbon footprint through low-carbon civil solutions
  • Maintain full site operation during construction

Scope of Works

  • Installation of Siltbuster tertiary MBBR unit
  • New MBBR feed pumping station
  • New de-gassing and final effluent sampling chambers
  • Ammonia/temperature instrumentation
  • New MCC, upsized transformer, MDP and standby generator
  • Soil stabilisation using tarmac bases to reduce embodied carbon
  • Strong in-house multidisciplinary delivery (Civils,M&E, PM, environmental)
  • Proven, compact MBBR technology reducing commissioning risk
  • Low-carbon civils approach through tarmac bases
  • Effective programme control and cross-team coordination
  • Early identification and resolution of ground condition constraints
  • Ongoing monitoring to ensure sustained ammonia compliance
  • Asset takeover and handover to operations by July 2026
  • Capture cost and programme data to benchmark future AMP8 MBBR schemes
  • Apply soil stabilisation and low-carbon civils learnings to similar sites
  • Future proofing enabled through installed Multimedia Filter infrastructure and transformer up scaling

General Enquiry

Build Smarter with BIMTek

Unlock the full potential of digital engineering with BIMTek Limited. By combining advanced 3D laser scanning, intelligent BIM modelling, and practical engineering expertise, we provide a connected approach that improves coordination across every stage of your project. Our workflows are designed to enhance visibility, minimise uncertainty, and help teams make informed decisions with confidence.

Whether you’re delivering complex infrastructure or tackling detailed design challenges, we focus on turning accurate data into clear, buildable solutions. From reducing costly errors to accelerating timelines, our team supports you with reliable insights and efficient processes—ensuring your project runs smoothly from initial concept through to final delivery.