To accelerate the AMP8 programme and de-risk downstream delivery, YTL onstruction fast-tracked early enabling works at Bishops Caundle WRC. By leveraging a standard product design and strong cross-disciplinary oordination, the team delivered a new ferric slab and bund ahead of schedule (mid-January 2026), enabling dry-installation of the ferric dosing unit before main works commence. The approach shortens installation time, reduces cost, and increases sequencing flexibility for the wider AMP8 scheme.